Re: Planner group to be changed in Equipment

$
0
0

Hello srinivas rao,


Change of Planner Groups in several equipments in mass:

If your system is EHP2 and above, you have a Carryout Mass change  option in GoTo in the menubar, through which you should be able to do. If your system is below EHP2, then you need to do it by LSMW which will be a very simple task for this job.

 

Plans

You need to change the Planner Groups of all plans created on these Equipments. It is a job of mass change of Plans,Tcode MCH01  is the answer.

 

 

Best of luck

KJogeswaraRao