Hi experts    

 

I have a question to the process chain variant "EXOR".

I read the help.sap.com for "collection process".

 

In development system I have executed this typ of process chain and must state that EXOR only started when the last predecessor process was finished!

 

I have not yet tested it in test system, but this behaviour is strange.

 

Our intention: The variants shown in the screen are part of a local chain in a "meta" chain.

The EXOR variant should start when the first predecessor variant (in our case it is "delete PSA request") starts.

This would start the successor local chain.

 

Is there a misunderstanding of EXOR?

 