Re: Schedule Call Plan Date

$
0
0

Hi Julie,

 

Please find below link about tolerance.

 

Tolerance - Maintenance Planning (CS-AG/PM-PRM-MP) - SAP Library

 

Below is the best example of the scheduling indicators provided by SAP

 

Example:

You schedule a maintenance plan with a monthly cycle
(for scheduling, one month is always 30 days long in the standard
system).

  • Time
    Today's date: 04/10/1998
    Next planned date: 03/11/1998 -> Today's date + 30 days
  • Key date
    Today's date: 04/10/1998
    Next planned date: 04/11/1998 -> Always on the 4th of the month
  • Factory calendar
    Today's date: 04/10/1998
    • Next planned date: 16/11/1998 -> Today's date (or next work day) + 30 work days

 

Based on the above you can define the scheduling indicator.

 

Rather than 100% give 10%, this might be helpful for you to understand the concept behind it.

 

Regards

Terence