Re: Question related to CIF of PDS to SCM

$
0
0

Hi Satish

 

 

Firstly you need to understand how Bom Explodes 

 

Example : Assume you have  Material X to manufacture X you required X1 X2,X3 .so now your Bom is 4 level .But you dont want  to explode all 4 levels .to avoid this you combine  x1,x2,x3 has Y by setting Phantoms assembly off . so now you are explodes in 2 level

 

 

If phantoms assembly is OFF (i.e 2 level ) you can go with selection of PDS directly by selecting PPDS

But if you want to explode each component in PDS(i.e 4level) then we will go for BOM

 

Only activation of integration model does not transfer PDS  to APO .After activating PDS in APO yo need to go Initial transfer By using TCODE : Curto_create . you need to insure actvation model is active

and all the BOM and Routing are correctly mantained in material master in ECC 

 

 

 

 

 

I hope this could help you in understanding

 

Regards

Virender